In order to provide complete functionality this website needs your consent to store browser cookies. If you don't allow cookies, you may not be able to use certain features of the website including,but not limited to log in, order services, see personalised content or switch between languages. It is recommended that you allow cookies. More information

The Electricity (Connection Offer Expenses) Regulations 2018

From 1st May 2018 we will be implementing changes to the way we recover some of the costs that we incur when preparing an offer for an electricity connection. If your proposed electricity connection requires work at 22kV and above we will charge you for the time we spend preparing the offer for connection in accordance with the Electricity (Connection Offer Expenses) Regulations 2018. We will require payment even if you do not accept the offer. The charge covers costs we reasonably incur when assessing the impacts of the proposed connection on the distribution/transmission system, designing the connection (including any reinforcement works) and preparing the offer.

We will invoice you at the same time as we issue the offer and you will be required to make payment within 28 days of issue.

The amount we charge will vary according to the complexity of the scheme based upon your requested capacity and the type of assets required to enable the connection. They will also vary according to whether you require an offer for WPD to undertake all the works or you request an offer for WPD to undertake only the non-contestable works and you employ an independent connection provider to undertake the rest.

Charges for WPD to undertake all the assessment and design works

Demand/DG Category Charge £
Demand Connection greater than 3MVA and up to 10MVA at EHV; 3,330
Connection greater than 10MVA and up to 50MVA; 4,089
Connection greater than 50MVA 5,603
Generation Connection of generation at EHV up to 10MVA; 4,656
Connection of generation at EHV greater than 10MVA; 5,035
Connection of generation greater than 50MVA 6,740

Charges for WPD to undertake only the non-contestable assessment and design works

Demand/DG Category Charge £
Demand Connection greater than 3MVA and up to 10MVA at EHV; 2,572
Connection greater than 10MVA and up to 50MVA; 2,952
Connection greater than 50MVA 4,467
Generation Connection of generation at EHV up to 10MVA; 3,709
Connection of generation at EHV greater than 10MVA; 4,277
Connection of generation greater than 50MVA 5,982

“EHV” in the tables above denotes the highest voltage of assets installed including any associated reinforcement or diversionary works.

The charge shown may increase if you ask us to undertake any additional work following receipt of your original application.

You can find further information on the application of charges in our Statement of Methodology and Charges for Connection by clicking here: Connections charging statements

We will contact you shortly after receiving your application to discuss your plans and then let you know the potential for EHV works to be required. Please note, that if you decide you no longer want to pursue your application and you notify us in writing within 10 working days of receiving our notification, we will not charge you. If you cancel after that time we may charge you for any costs reasonably incurred up to the point of notification.

If you have any queries regarding the application of the charges please contact the Design Engineer notified to you as being responsible for your application. If, following discussion, you are not satisfied with our response and we cannot resolve the matter you may escalate it further. Our complaints procedure is available to view on our website www.westernpower.co.uk If you do not feel we have dealt with your complaint satisfactorily you may also refer the matter to the Authority for determination in accordance with section 23 of the Electricity Act 1989.