Export Capacity Recovery

Releasing export capacity from existing customers

As part of Ofgem’s consultation process in to Quicker and More Efficient Connections (QMEC) it was clear that the requirement to reinforce the distribution system (and the associated costs) was one of the biggest factors in influencing the timescale for connection. Reinforcement is required for both demand and distributed generation (DG) type connections but the extremely high volumes of DG applications made, due in part to the various Government incentives, have put a tremendous strain on the distribution system to the extent now that, due to connected and committed capacity, much of WPD’s network is operating at its limits so that significant reinforcement is required before further generation can be accommodated.