Design approval quarterly report

The table below details the time taken (minimum, maximum and average) for responding to requests from Independent Connection Providers (ICPs) for design approval. The number of requests are brown down by market segment.

This data represents the period of 1st April 2021 - 30th June 2021.

Market Segment

Design Approved


Design Rejected
 
MinMaxAverageTotalMinMaxAverageTotal


EHV Demand
 

00011313131


EHV Generation
 

6141026

8

72


HV Demand
 

01058501069


HV Generation
 

88810000


LV Demand
 

0104115010513
 

LV Generation
 

00000000